FS#7790 — Transfert de ligne

Attached to Project— Datacenters
Maintenance
Beauharnois
CLOSED
100%
Ce mercredi 19/12/2012 vers 8h30 EST / 14h30 CET, nous allons effectués un transfert de ligne sur notre poste 120kV.

Il n'y a pas de coupure à prevoir.
Date:  Wednesday, 19 December 2012, 15:51PM
Reason for closing:  Done
Additional comments about closing:  Le transfert est effectué.