FS#7493 — Test transformateur secours

Attached to Project— Datacenters
Maintenance
Roubaix 2
CLOSED
100%
Nous allons procéder a des tests de transformateur de secours a RBX2.
TGBT 5 et 7 prévus en cette fin de matinée.
Date:  Thursday, 18 October 2012, 15:25PM
Reason for closing:  Done
Additional comments about closing:  Les tests ont été concluants.