rssLink RSS for all categories
 
icon_red
icon_green
icon_red
icon_blue
icon_red
icon_green
icon_green
icon_orange
icon_red
icon_red
icon_green
icon_green
icon_green
icon_orange
icon_green
icon_green
icon_green
icon_blue
icon_red
icon_red
icon_green
icon_green
icon_green
icon_blue
icon_orange
icon_blue
icon_green
icon_green
icon_green
icon_green
icon_red
icon_red
icon_green
icon_green
icon_green
icon_green
 

FS#53350 — [SBG3][Cooling system] AC MS9 - Pump 1 and 2

Attached to Project— Datacenters
Maintenance
Strasbourg   → SBG-3
CLOSED
100%
Start time : 28/09/2021 06:30 UTC
End time : 28/09/2021 15:00 UTC
Service impact : None
Service improvement : Pump 1 and 2 preventive replacement on air cooling MS9
-------------
Heure de début : 28/09/2021 06:30 UTC
Heure de fin : 28/09/2021 15:00 UTC
Impact sur le service : Aucun
Amélioration du service : Remplacement préventif des pompes 1 et 2 sur AC MS9
Date:  Tuesday, 28 September 2021, 16:37PM
Reason for closing:  Done