FS#46724 — RBX4 - UPS1,2,3,4

Attached to Project— Datacenters
Maintenance
Roubaix   → RBX-4
Planned
0%
Résumé: Nous allons procéder à une maintenance périodique des UPS.
Datacentres affectés: RBX4 - UPS1,2,3,4
Impact: aucun
Debut: 29/Sep/20 08:00 (UTC+2)
Fin: 30/Sep/20 17:00 (UTC+2)



Summary: We will perform a periodic maintenance of the UPS.
Affected datacenters: RBX4 - UPS1,2,3,4
Impact: none
Start: 29/Sep/20 08:00 (UTC+2)
End: 30/Sep/20 17:00 (UTC+2)