FS#44418 — Gra1 - UPS

Attached to Project— Datacenters
Maintenance
Gravelines   → GRA-1
CLOSED
100%
Résumé : Nous allons effectuer l'entretien périodique des UPS.
Datacentre affectée : GRA1
Impact : Aucun.
Début : 19/05/2020 10h00 UTC+2
Fin : 19/05/2020 18h30 UTC+2

Summary: We will carry out the periodic maintenance of the UPS.
Affected datecenter: GRA1
Impact: None.
Start : 05/19/2020 10:00 AM UTC+2
End : 05/19/2020 6:30 PM UTC+2
Date:  Sunday, 05 July 2020, 07:18AM
Reason for closing:  Done