FS#42827 — RBX UPS

Attached to Project— Datacenters
Maintenance
Roubaix
CLOSED
100%
Résumé: Nous allons procéder à une maintenance périodique des UPS.
Baies affectées: RBX
Impact: aucun
Dates:
Lundi 10 février 2020 de 9H à 13h à RBX 2 et 4 (GMT+1)
Mercredi 12 février 2020 de 9h à 13h à RBX 1 et 3 (GMT+1)
Lundi 17 février 2020 de 9h à 13h à RBX 5,6 et 7 (GMT+1)


Summary: We will perform a periodic maintenance of the UPS.
Affected racks: RBX
Impact: none
Dates:
Monday, February 10th 2020 from 9H to 13h at RBX 2 and 4 (GMT+1)
Wednesday, February 12th 2020 from 9h to 13h at RBX 1 and 3 (GMT+1)
Monday, February 17th 2020 from 9h to 13h at RBX 5,6 and 7 (GMT+1)
Date:  Thursday, 26 March 2020, 16:10PM
Reason for closing:  Done
Comment by OVH - Thursday, 26 March 2020, 16:10PM

Intervention terminée.