FS#42454 — L112B01

Attached to Project— Network and racks
Maintenance
Limburg   → LIM-1
CLOSED
100%
Résumé: Nous avons detecté un défaut sur le switch de baie qui nécessite son remplacement.
Actions: Remplacement du switch.
Debut: 18 Janvier 2020 a partir de 4h00 AM GMT+1
Baies affectées: L112B01
Impact: Coupure du réseau public le temps du remplacement.
Durée estimée : 1h

Summary: We have detected a fault on the switch which requires replacing.
Actions: Replace switch.
Start: January 18th 2020 starting at 4:00 AM GMT+1
Affected racks: L112B01
Impact: Disconnection of the public network during the replacement time.
Estimated time: 1h
Date:  Saturday, 18 January 2020, 05:00AM
Reason for closing:  Done
Comment by OVH - Saturday, 18 January 2020, 04:04AM

Nous débutons le remplacement.

We are starting the replacement.


Comment by OVH - Saturday, 18 January 2020, 04:40AM

Le nouveau switch est en place, nous travaillons à rétablir la communication de chacun des serveurs.

The new switch is in place, we are working on reestablishing the communication to all servers.


Comment by OVH - Saturday, 18 January 2020, 04:58AM

Intervention terminée, tous les serveurs sont accessibles.

Intervention done, all servers are accessible.