FS#42337 — UPS 3B

Attached to Project— Datacenters
Maintenance
Warsawa   → WAW-1
Planned
0%
Resumé : Nous allons effectuer la maintenance de UPS 3B
Debut : 21 janvier 2020 - 9:00 UTC+1
Rack affectée : W14
Impact : Aucun
Fin estimée : 21 janvier 2020 16h00 UTC+1

Summary : We will perform the maintenance of UPS 3B
Start : January 21st 2020 - 9.00AM UTC+1
Affected Rack : W14
Impact : None
Estimated End : January 21st 2020 16:00 PM UTC+1