FS#41854 — G217, G253, G254, G232, G242

Attached to Project— Datacenters
Maintenance
Gravelines   → GRA-2
CLOSED
100%
Résumé : Nous allons procéder à des améliorations sur la distribution électrique de cette salle
Debut : 10/12/2019 - 9:00 (UTC+1)
Salle affectée : G217, G253, G254, G232, G242
Impact : Aucun
Fin : 10/12/2019 - 15:00 (UTC+1)

Summary : We will make improvements to the electrical distribution of this room
Start : 12/10/2019 - 9:00 AM (UTC+1)
Affected room : G217, G253, G254, G232, G242
Impact : None
End : 12/10/2019 - 3:00 PM (UTC+1)
Date:  Wednesday, 18 December 2019, 15:31PM
Reason for closing:  Done