FS#41849 — Salle 0 BHS

Attached to Project— Datacenters
Maintenance
Beauharnois
CLOSED
100%
Resumé : Nous allons effectuer l'entretiens des clims dans les salles 0 des BHS
Debut : 10/12/2019 8:00 (UTC-4)
Baie affectée : Salle 0
Impact : Aucun
Fin : 11/12/2019 17:00 (UTC-4)


Summary : We will perform the maintenance of the air conditionning system in the Room 0 of BHS
Start : 12/10/2019 8:00 AM (UTC-4)
Affected Rack : Room 0
Impact : None
End : 12/11/2019 17:00 PM (UTC-4)
Date:  Wednesday, 18 December 2019, 15:31PM
Reason for closing:  Done