FS#41361 — G205A + G205B

Attached to Project— Datacenters
Maintenance
Gravelines   → GRA-2
Planned
0%
Résumé : Nous allons effectuer des améliorations électrique dans les baies suivantes.
Début : 20/11/2019 a partir de 10h00 UTC+1
Baies affectées : G205A + G205B
Impact : Aucun
Durée estimée : 1h

Summary: We will make electrical improvements in the following racks.
Start: 11/20/2019 starting at 10:00 AM UTC+1
Assigned racks: G205A + G205B
Impact: None
Estimated time: 1h