FS#41358 — Ge LIM

Attached to Project— Datacenters
Maintenance
Limburg   → LIM-1
Planned
0%
Résumé : Nous allons effectuer les tests des groupes électrogènes du site.
Début : 27/11/2019 11h00 UTC+1
Datacentre Affecté: LIM1
Impact : Aucun.
Fin estimée : 27/11/2019 17h00 UTC+1

Summary: We will test the generators of the entire site.
Start: 11/27/2019 11:00 AM UTC+1
Affected datecenter: LIM1
Impact: None.
Estimated end: 11/27/2019 5:00 PM UTC+1