Test UPS
Scheduled Maintenance Report for Network & Infrastructure
Completed
Resumé : Nous allons effectuer un test des UPS
Debut : 13/11/2019 - 9:00 UTC+1
Rack affectée :
13/11/19 : RBX2, RBX4, RBX5 et RBX6
18/11/19 : RBX1 et RBX3
25/11/19 : RBX7
Impact : Aucun
Fin estimée : 25/11/2019 - 14:00 UTC+1

Summary : We will perform an UPS test
Start : 11/13/2019 - 10.00 AM UTC+1
Affected Rack :
13/11/19 : RBX2, RBX4, RBX5 and RBX6
18/11/19 : RBX1 and RBX3
25/11/19 :RBX7
Impact : None
Estimated End : 25/11/2019 - 2:00 PM UTC+1

Update(s):

Date: 2019-11-22 14:00:55 UTC
Nous prolongeons les tests UPS de RBX7 jusqu'au 25 novembre.

We extend the RBX7 UPS tests until Nov, 25.