FS#38964 — G104 / G114

Attached to Project— Datacenters
Maintenance
Gravelines   → GRA-1
CLOSED
100%
Résumé : Nous allons ajouté un nouveau circuit au système de refroidissement
Début : 17/06/19 8h00 UTC+2
Baie : G104 / G114
Impact : Aucun
Fin : 04/07/19 17h00 UTC+2

Summary : We will add a new way on the Cooling System
Start : 06/17/19 8:00 AM UTC+2
Rack : G104 / G114
Impact : None
End : 07/04/19 5:00 PM UTC+2
Date:  Wednesday, 03 July 2019, 21:15PM
Reason for closing:  Done
Additional comments about closing:  done
Comment by OVH - Thursday, 27 June 2019, 10:14AM

La maintenance est prolongée jusqu'au 04/07*19 17h00 UTC+2.

Maintenance windows is extended until 07/04/19 5:00 PM UTC+2.


Comment by OVH - Wednesday, 03 July 2019, 21:15PM

Intervention complétée

Intervention completed