FS#38886 — 46A 46B 46C 46D13 a/to 46D31

Attached to Project— Datacenters
Maintenance
Roubaix   → RBX-6
CLOSED
100%
Résumé : Nous allons effectuer une intervention sur la partie cooling de ces salles.
Début : 19/06/19 09h00 UTC+2
Baie : 46A 46B 46C 46D13 a 46D31
Impact : Aucun
Fin : 20/06/19 17h00 UTC+2

Summary : We will perform a intervention on the cooling part of those rooms.
Start : 06/19/19 9:00 AM UTC+2
Rack : 46A 46B 46C 46D13 to 46D31
Impact : None
End : 06/20/19 5:00 PM UTC+2
Date:  Thursday, 25 July 2019, 13:56PM
Reason for closing:  Done