FS#38579 — T04B21 to T04B39

Attached to Project— Datacenters
Amélioration
Beauharnois   → BHS-4
CLOSED
100%
Summary : We will make improvements to the electrical distribution part of these racks.
Start : 28 May 2019 - 7 Am UTC-4
Affected Racks : From T04B21 to T04B39
Impact : None.
End : 30 May 2019 - 16 PM UTC-4
Date:  Thursday, 25 July 2019, 13:55PM
Reason for closing:  Done