Storage GRA
Scheduled Maintenance Report for Public Cloud
Completed
On January 21st your storage services on some Cloud Instances in our GRA Datacenter will move to the Jewel release 10.2.10 of CEPH (https://ceph.com/releases/v10-2-10-jewel-released/ ).
The maintenance will start at 22:00 AM CET (21:00 UTC) for an estimated duration of 36 hours. During the operation, your storage backend will remain available.

From January 14th you may notice loss of l/O performance on your disks due to a preventive backup of the entire cluster that will be carried by our technical teams. Want to discover more about that https://fosdem.org/2018/schedule/event/backup_ceph_at_scale/


Update(s):

Date: 2019-02-07 13:11:10 UTC
Operation done.

Date: 2019-02-07 07:41:20 UTC
Operation slowly moving towards finish.
~85% done.

Date: 2019-02-06 13:44:28 UTC
We reduced impact on cluster by slowing down the operation.

Date: 2019-02-04 21:08:34 UTC
Operation started.

Date: 2019-01-21 12:40:02 UTC
Operation has been postponed 14 days. We will start on February 4th at 22:00 AM CET (21:00 UTC).
Posted Jan 14, 2019 - 12:22 UTC