Get webhook notifications whenever Network & Infrastructure creates an incident, updates an incident, resolves an incident or changes a component status.
Résumé : Nous allons intervenir sur la climatisation de la salle
Actions : Maintenance de la climatisation
Début : 15 février 2018 à partir de 10h30AM (UTC +1)
Baies affectées : Salle 25
Impact : Aucun. Le système est redondant
Fin estimée : 15 février 2018 à 11h30AM (UTC +1)
Summary : We will intervene on the air conditioning of the room
Actions : Maintenance of the air conditioning system
Start : February 15th 2018 at 10h30AM (UTC +1)
Affected Rack : Room 25
Impact: None. The system is redundant
Finish Time : February 15th 2018 at 11h30AM (UTC +1)
Update(s):
Date: 2018-02-15 10:43:25 UTC Intervention terminée
Intervention done
Date: 2018-02-15 09:46:28 UTC Nous commençons l'intervention
We start
Posted Feb 13, 2018 - 13:06 UTC
This scheduled maintenance affected: Infrastructure || RBX (RBX2).